Millennium Tower
Location: Rotterdam
Brief description: Hotel and Office Tower
Architect: AGS Architekten & Planners B.V. of Heerlen
Engineer: D3BN of Amsterdam
Contractor: Bouwcombinatie Weena Toren V.O.F.
Originally designed with hollow core slab, late in the
design stage it was determined that Bubbledeck would
allow for considerable cost and time savings.
Another consideration was the lack of storage space on
the building site which is located close to heavy traffic
highways and streets. The floors were finished in half the
time on average (4 days instead of 8) and the number of
floors was increased by 2 up to 34th. level while the same
overall building elevation .was maintained.
The building was completed in April 2000. |
 |